Here is a model constructed in TBC for volume Computations. The Original ground had to have an extra excavation removed from it before we could do the volumes to it due to the tender requirements. Cleaned up the Design model and computed the Cut Fill volumes at the press of a button. Volume Comps are a breeze with TBC. 


Let Sherozearthworks DataPrep help you work out those tricky Volume Comps.....



Earthworks Volume Report

Original surface compared to Design surface

Surfaces
OG-With EarlyWorks Classification: Original
Design-FSL Classification: Design


Volumes from Surface Geometry
Difference 114,006.5 m³

Material excavated 119,182.5 m³
Material placed 5,176.0 m³

Areas from Surface Geometry

Area excavated 71,196.6 m²
Area placed 14,685.3 m²
Zero volume area 4.1 m²
Total 85,886.0 m²

Depth summary

Maximum depth of excavated material 5.274 m
Maximum depth of placed material 1.933 m


Data Preparation and Aerial Survey


InstagramFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)
Facebook FFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)

Follow us for Updates

Contact Sheroz Earthworks now for a Free quote.

Get a free quote today by filling out the online form, or speak with a member of our team now by calling us.

Contact us

Get a free quote today 

Contact us for quote or general query with the form below